Stage Reports

Stage Reports

Bayou Crossing

Processed

Andres Rivera · QC

Visit

Subdivision
Bayou Crossing
Daily Crew
Submitted By
Andres Rivera
Role
QC

Subdivision Summary

Full Bins
45
Hrs to Empty
3.9
Truckloads
1.9
Truck Issues
Material pallets blocking two driveways
Usefulness
4
Status
Processed
20 records
Blk 9 Lot 100Rough Framing2Correct LocationEmptied
Lot 98Pre-Framing1Correct LocationEmptied
Lot 21Pre-Framing2Correct LocationBin Missing
Lot 230Framing2Correct LocationEmptied
Extra:House Sweep — mattress in binOpen
Lot 21Rough Framing2TBDLeft Full
Extra:House Sweep — sofa left at curbOpen
Blk 2 Lot 10Pre-Framing2Correct LocationLeft Full
Blk 4 Lot 188Framing1Correct LocationLeft Half Full
Lot 50Pre-Framing2Correct LocationBin Missing
Blk 2 Lot 102Rough Framing1Correct LocationEmptied
Lot 48Framing2Correct LocationEmptied
Lot 225Framing2Correct LocationLeft Full
Lot 147Pre-Framing2Correct LocationEmptied
Lot 137AFraming2Correct LocationEmptied
Lot 237Framing2Correct LocationLeft Half Full
Lot 157Framing2TBDEmptied
Blk 7 Lot 226Framing1Correct LocationBin Missing
Lot 65Framing1Correct LocationLeft Half Full
Lot 106Rough Framing2TBDLeft Half Full
Lot 155Framing2Correct LocationEmptied
Lot 36Pre-Framing2Correct LocationLeft Half Full